Cementing and Displacement Procedures -Single Stage
Single Or First Stage

- Line up to the rig mud pumps. Break circulation slowly. When it has been determined that full returns have been established, gradually increase the pump rate and circulate total hole volume. Record the pressures at the various flow rates. At the end of circulation, record the pressure with estimated displacement rate.
- During circulation monitor pit levels, bottoms-up mud properties and eventual shows.